Reply
Regular Visitor
Posts: 34
Registered: ‎11-09-2015

Re: Determine if date is between 2 dates

Community Support Team
Posts: 7,674
Registered: ‎05-02-2017

Re: Determine if date is between 2 dates

Hi @Silko,

 

I'm glad it can help you. Please open a new thread of your question.

 

Best Regards,

Dale

Community Support Team _ Dale
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Highlighted
Regular Visitor
Posts: 34
Registered: ‎11-09-2015

Re: Determine if date is between 2 dates

Here is the new thread. I was not sure what the subject should be so it was simpler to ask the question here. Smiley Happy

Member
Posts: 62
Registered: ‎07-07-2017

Re: Determine if date is between 2 dates

Hello @v-jiascu-msft ,

 

Your solution may help my case too. Can you please tell me what is the relationship between the two tables (quarters and calendar tables) you are using? (i.e. what datafields in the two tables you are using to connect the two tables?)

 

Everything works fine for me in the formula until the function EARLIER. Just after the EARLIER function when I am trying to type the date field from my calendar table I don't have the list of the available data fields to choose it. I believe I did not connected the two tables properly. I tried to connect the field "Start date" in Quarters table with field "Date" in date teble (not sure if this is correct). 

 

Many thanks

Community Support Team
Posts: 7,674
Registered: ‎05-02-2017

Re: Determine if date is between 2 dates

Hi @MariosChr90,

 

Actually, no relationship is there. No EARLIER is needed either. Please refer to the file in the attachment. I have improved it.

 

Best Regards,
Dale

Community Support Team _ Dale
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.