Dax formula for calculating no. of projects from past 30 days, past 30 - 60 days and < 60 days

Hi ,

I have a requirement where I need to calcuate "Number of projects created" for last 30 days, 30-60 days and above 60 days.

I have two date columns "actual start date" and "Expected delivery date".

 
no of days = DATEDIFF('Work in Progress'[Actual Start date],'Work in Progress'[Estimated Delivery/Close date],DAY)
 
Using above formula i am getting no of days between two dates but i need projects between 30,30-60 and above 60.
1 ACCEPTED SOLUTION
v-tangjie-msft
Community Support
Community Support

Hi @shyamily_123 ,

 

According to your description , you mean counting the number of projects with a project time of 30 days, 30-60 days, and more than 60 days, right? Here are my steps you can follow as a solution.

(1) This is my test data. 

vtangjiemsft_0-1671003444585.png

 

(2) We can create calculated columns.

Column = var a=DATEDIFF('Table'[Actual start date],'Table'[Expected delivery date],DAY)

return SWITCH(TRUE(),a<30,"<30",a>=30&&a<=60,"30~60",a>60,">60")
Column 2 = COUNTAx(FILTER('Table','Table'[Column]=EARLIER('Table'[Column])),[Column])

(3) Then the result is as follows.

vtangjiemsft_3-1671003574065.png

If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

 

Best Regards,

Neeko Tang

If this post  helps, then please consider Accept it as the solution to help the other members find it more quickly. 

View solution in original post

1 REPLY 1
v-tangjie-msft
Community Support
Community Support

Hi @shyamily_123 ,

 

According to your description , you mean counting the number of projects with a project time of 30 days, 30-60 days, and more than 60 days, right? Here are my steps you can follow as a solution.

(1) This is my test data. 

vtangjiemsft_0-1671003444585.png

 

(2) We can create calculated columns.

Column = var a=DATEDIFF('Table'[Actual start date],'Table'[Expected delivery date],DAY)

return SWITCH(TRUE(),a<30,"<30",a>=30&&a<=60,"30~60",a>60,">60")
Column 2 = COUNTAx(FILTER('Table','Table'[Column]=EARLIER('Table'[Column])),[Column])

(3) Then the result is as follows.

vtangjiemsft_3-1671003574065.png

If the above one can't help you get the desired result, please provide some sample data in your tables (exclude sensitive data) with Text format and your expected result with backend logic and special examples. It is better if you can share a simplified pbix file. Thank you.

 

Best Regards,

Neeko Tang

If this post  helps, then please consider Accept it as the solution to help the other members find it more quickly. 

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.