I have to create the datediff between the 'project from date' and 'today' in days. 
However I am not able to specify 1st date parameter column.

Is there a way I can calculate difference between 2 dates?

1 ACCEPTED SOLUTION
v-yadongf-msft
Community Support
Community Support

Hi @chaitanyajiwani ,

 

There are two solutions:

 

1.Please create a new column:

 

Column = DATEDIFF('Table'[project from date],TODAY(),DAY)

 

vyadongfmsft_0-1661335635571.png

 

2.Please create a new measure:

 

 

gap = DATEDIFF(MAX('Table'[project from date]),TODAY(),DAY)

 

vyadongfmsft_1-1661335635573.png

 

Best regards,

Yadong Fang

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

View solution in original post

5 REPLIES 5
v-yadongf-msft
Community Support
Community Support

Hi @chaitanyajiwani ,

 

Has your problem been solved? If solved, please consider Accept it as the solution to help the other members find it more quickly.

v-yadongf-msft
Community Support
Community Support

Hi @chaitanyajiwani ,

 

There are two solutions:

 

1.Please create a new column:

 

Column = DATEDIFF('Table'[project from date],TODAY(),DAY)

 

vyadongfmsft_0-1661335635571.png

 

2.Please create a new measure:

 

 

gap = DATEDIFF(MAX('Table'[project from date]),TODAY(),DAY)

 

vyadongfmsft_1-1661335635573.png

 

Best regards,

Yadong Fang

If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Tahreem24
Super User
Super User

@chaitanyajiwani ,Try this

DATEDIFF(TableName[Proj Start Date Column],Today(),DAY)

 

Don't forget to give thumbs up and accept this as a solution if it helped you!!!

Please take a quick glance at newly created dashboards : Restaurant Management Dashboard , HR Analytics Report , Hotel Management Report, Sales Analysis Report , Fortune 500 Companies Analysis , Revenue Tracking Dashboard

I tried that, but I am not able to add the first date parameter is i.e. 'Project From Date' column.

Hi @chaitanyajiwani 
Please try
DATEDIFF ( SELECTEDVALUE ( TableName[Proj Start Date Column] ),  Today ( ), DAY )

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.