Say I have a table of projects with start date, end date, total workload and responsible. I want to be able to show the average workload on all responsible for each day in the range.

A very simple case:

Project: #1

Start: 1/1-2018
End: 5/1-2018
Total workload: 10 hours
Responsible: Peter

 

Project: #2
Start: 3/1-2018
End: 5/1-2018

Total workload: 6 hours
Responsible: Peter

Would render the following:
Peters average workload for week 1
Monday: 2 hours
Tuesday: 2 hours
Wednesday: 4 hours
Thursday: 4 hours
Friday: 4 hours

Any tips on this?

//M

8 REPLIES 8
Morten Frequent Visitor
Frequent Visitor

Re: Date range even distribution

Here's a screenshot of my sample data:

SampleData.PNG

Community Support Team
Community Support Team

Re: Date range even distribution

@Morten,

 

Add a calendar table and use measure below.

Measure =
VAR d =
    SELECTEDVALUE ( 'Calendar'[Date] )
RETURN
    SUMX (
        FILTER ( Table1, Table1[Start] <= d && Table1[End] >= d ),
        Table1[LoadPrWorkDay]
    )
Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Morten Frequent Visitor
Frequent Visitor

Re: Date range even distribution

Thanks! When you say a calendar table do you mean a data table containing of just dates? And if so does it need to be linked to the project table or not?

Community Support Team
Community Support Team

Re: Date range even distribution

@Morten,

 

Yes, no need to set relationship.

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Highlighted
Morten Frequent Visitor
Frequent Visitor

Re: Date range even distribution

@v-chuncz-msft

 

I'm getting closer, but it does not seem to do quite what I'm looking for still.

In week 1 Peter has a project, which starts the 3rd of january and ends the 31st of january. This is what I'm getting:
Workload.PNG

But I'm really needing it to make it look like this:
Wednesday 1,19
Thursday 1,19
Friday 1,19

For alle the days in the project.

Can that be done?

Community Support Team
Community Support Team

Re: Date range even distribution

@Morten,

 

Drag [Date] from calculated table as shown below.

 

Calendar =
CALENDARAUTO ()

 

 

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
Morten Frequent Visitor
Frequent Visitor

Re: Date range even distribution

@v-chuncz-msft

Uhm I might not fully understand what you're asking me to do, but now I've created yet another table, but that didn't really do much of a difference?

Morten Frequent Visitor
Frequent Visitor

Re: Date range even distribution

Still looking for input to get the solution I need 🙂

Helpful resources

Announcements
Coming Soon: T-Shirt Design Contest

Coming Soon: T-Shirt Design Contest

Keep your eyes open for our upcoming T-shirt design contest!

Meet the 2020 Season 1 Power BI Super Users!

Meet the 2020 Season 1 Power BI Super Users!

It’s the start of a new Super User season! Learn all about the new Super Users and brand-new tiered recognition system.

Super User Challenge: Can You Solve These?

Super User Challenge: Can You Solve These?

We're celebrating the start of the New Super User season with our first ever Super User 'Can You Solve These?' challenge.

Power BI Desktop Update - February 2020

Power BI Desktop Update - February 2020

We are super excited for our update this month, as we are releasing two of our top community requests!

Power Platform Online Conference

Power Platform Online Conference

Join us for the first ever Power Platform Online Conference!

Top Solution Authors