DAX Count, Summarize, Groupby, Filter

Hi,

 

I have got a query in power bi and the table what I'm trying to group or summarize then count has various coloums.

 

I want to show a cummulative % graph of Start, Finish Plan VS Start, Finish Actual by discipline.

 

Discipline / Plan Start Date/ Actual Start Date/ Plan Finish Date/ Actual Finish Date  

Piping/        04/12/2018/       01/02/2019/         04/01/2019/          08/02/2019

Piping/        06/12/2018/       01/02/2019/         04/01/2019/          08/02/2019

Piping/        05/12/2018/       01/02/2019/         04/01/2019/          08/02/2019

Piping/        07/12/2018/       01/02/2019/         04/01/2019/

Structure/    04/01/2019/                                   05/02/2019/

Structure/    04/01/2019/                                   05/02/2019/

Structure/    03/01/2019/                                   05/02/2019/

Structure/    04/01/2019/       08/02/2019/        05/02/2019/

Machanical/ 04/01/2019/                                  06/02/2019/

Machanical/ 05/04/2019/                                  06/02/2019/

Machanical/ 05/07/2019/       08/02/2019/       06/02/2019/

 

 

What I need to group or summarize then count is look so:

- Calendar: have earliest to latest dates above talbe has 

- for cumulative need to count blank as 0

- Total Number of Piping

 

Piping Table

Calendar/      Plan Start Date/ Actual Start Date/ Plan Finish Date/ Actual Finish Date / Plan Start Cul/ Total number

01/12/2018             1                         1                          1                              1                          1                      80

02/12/2018             2                         2                          1                              2                          3                      80

03/12/2018             4                         2                          1                              3                          7                      80

04/12/2018             1                                                                                                                 8                      80

        .                                                                                                                                          .                       80

        .                                                                                                                                          .                       80

        .                                                                                                                                          .                       80

05/02/2019                                                                    1                                                          8                      80

06/02/2019                                        1                          2                                                          8                      80

07/02/2019             1                         1                          2                                                          9                      80

08/02/2019                                                                                                                                9                      80

 

 

The goal is to take counted table by discipline to create cumulative graph that have 4 lines (Start plan date, Start actual date, Finish plan date and Finish actual date).  

 

Thanks in advanced for any help.

 

 

The goal from;

 

I've made a graph like so;

the problem is when i filter dicipline Piping ,for example, in the slicer.

It doesn't show from 0% to 100%.  so trying to make each dicipline tables.!

 what i have.PNG

3 REPLIES 3
v-chuncz-msft
Community Support
Community Support

@colourfullife,

 

You may research the code generated by Quick measure Running total.

Community Support Team _ Sam Zha
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.

Hi, thanks for your reply.

 

I've been trying to play around the quick measure..

It doesn't get me what i want.

 

i attached the file i working with. can you show me how it works?

 

thank you,

Here is the native file attached.

 

There is a cumulative graph have 4 lines (Start plan/ Start Actual/ Finish plan/ Finish Actual) with slicers.

what makes me head bang is when i choose any options in slicer. want to see 0%-100% lines graph.?

 

1. Do i need to measure every single slicer's options?

2. what if i want to choose more than 2 options from slicer?

 

Many thanks for any help.

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.