Hi All,

 

I have around 30 reports in QA, IS there a way I can automatically change connections from QA to Prod?

 

Thanks,
Aditya 

1 REPLY 1
Highlighted
Community Support Team
Community Support Team

Re: Change All Connections

Hi @adityakommu,

 

Unfortunately, there is no automatic way to change connections from QA to Prod.


I think here we can only change the connection one by one. There are two options for you to change data source currently. Here I made a test based on SQL Server database.

 

Option1:File Menu –  Options and Settings – Data Source settings. Here we can change the server from QA to Pord. After that we need to edit the permission if necessary.

 

Capture.PNG

 

Option2: in the “Edit Queries” menu, we can change the code like this:

let
   Source = Sql.Databases("sqldatabaseprod"),
    databasename = Source{[Name="Test"]}[Data],
    dbo_Tablename = databasename{[Schema="dbo",Item=" Tablename "]}[Data]
in
dbo_ Tablename

 

In addition, You could submit this feature request at Idea page, your feedback is valuable to improve the level of our products. Thanks for your understanding.


Regards,
Frank

Community Support Team _ Frank
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.