Reply
spandy34
Responsive Resident
Responsive Resident

Calculating time Midnight

I have the table below.  I have a Plannned Entry Time and a Planned Exist Time and a Planned Duration which are all Time fields.  I have used the following formula for the Planned Duration Column

Planned Duration = [PlannedExitTime]-[PlannedEntryTime].  It works okay until like the example the Planned Entry TIme is 23:45:00 and then the Planned Exit Time is Midnight.  The Planned Duration states 23:45:00 instead of 00:15:00
 
Can someone help with the formula in the Planned Duration Column to resolve this please.

@amitchandak @Greg_Deckler 

 

spandy34_0-1678813451109.png

 

1 ACCEPTED SOLUTION

THis has solved it - thank you so much for your help

Planned Duration =
  IF(
    [PlannedExitTime] = TIME(0,0,0),
   (TIME(23,59,59)- 'Procurement_Main_Data'[PlannedEntryTime])+TIME(0,0,1),
   [PlannedExitTime] - [PlannedEntryTime]
  )

View solution in original post

7 REPLIES 7
Greg_Deckler
Super User
Super User

@spandy34 Is this being done in Power Query?

 


@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...

No not power query . I just added the column in the table imported from an sql database 

@spandy34 OK, try this:

Planned Duration = 
  IF(
    [PlannedExitTime] = TIME(0,0,0),
    (TIME(23:59:59) - [PlannedEntryTime) + TIME(0,0,1),
    [PlannedExitTime] - [PlannedEntryTime]
  )

@ me in replies or I'll lose your thread!!!
Instead of a Kudo, please vote for this idea
Become an expert!: Enterprise DNA
External Tools: MSHGQM
YouTube Channel!: Microsoft Hates Greg
Latest book!:
The Definitive Guide to Power Query (M)

DAX is easy, CALCULATE makes DAX hard...

THis has solved it - thank you so much for your help

Planned Duration =
  IF(
    [PlannedExitTime] = TIME(0,0,0),
   (TIME(23,59,59)- 'Procurement_Main_Data'[PlannedEntryTime])+TIME(0,0,1),
   [PlannedExitTime] - [PlannedEntryTime]
  )

Hi @Greg_Deckler 

 

Ive tried adding a column with the above Dax and I am getting the error below

spandy34_0-1678820167105.png

 

AndrewPF
Helper V
Helper V

Are you taking into account the fact that anything after midnight is the following day? 

Do your time fields include a date? 

See also: 

Solved: Concatenate date and time from different columns i... - Microsoft Power BI Community

spandy34
Responsive Resident
Responsive Resident

no it doesn't include a date. I think that was the problem . I think I need some DAX thst says if the time equals midnight then it's handled differently than just [PlannedExitTime]-[PlannedEntryTime]

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.