Calclulating Days between 2 dates in the edit query

Hey,

 

Is there a way that I can calculate the number of days between 2 dates in the edit query option itself. The DatedIFf Formula does not work in the add custom columns. It says it cannot be recognized.

 

Is there any other syntax or formula that can be used? Thank You!

1 ACCEPTED SOLUTION
Zubair_Muhammad
Community Champion
Community Champion

@Anonymous

 

Try with following custom column

 

=Duration.Days(Duration.From([End]-[Start])))

Regards
Zubair

Please try my custom visuals

View solution in original post

1 REPLY 1
Zubair_Muhammad
Community Champion
Community Champion

@Anonymous

 

Try with following custom column

 

=Duration.Days(Duration.From([End]-[Start])))

Regards
Zubair

Please try my custom visuals

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.