Budget vs Actual Cost Analysis with Dial Guage

I am trying to Show dial Guage for Actual vs Budget Cost.

 

As it is a Cost ,

 

  • If Actual is -10% (less than) Budget then it should be Green
  • If Actual is withing +/- 10% of Budget then Yellow
  • If Actual is +10 % (Greater Than) budget then Red

 

For sale its easy but for cost the dial guge should be revearsed. 

 

 

1 ACCEPTED SOLUTION

Accepted Solutions
otravers Member
Member

Re: Budget vs Actual Cost Analysis with Dial Guage

5 REPLIES 5
v-yulgu-msft Super Contributor
Super Contributor

Re: Budget vs Actual Cost Analysis with Dial Guage

Hi @purana2002,

 

For dial Guage, here is video for your reference. 

 

To get more advice, please illustrate your scenario with more details, please share sample data and desired result.

 

Regards,

Yuliana Gu

Community Support Team _ Yuliana Gu
If this post helps, then please consider Accept it as the solution to help the other members find it more quickly.
purana2002 Regular Visitor
Regular Visitor

Re: Budget vs Actual Cost Analysis with Dial Guage

I am trying to show Cost instead of Sale on Dial Guage,

 

Example,

 

Cost Budget is $100.

 

  • If the Actual cost is 10% less than Budget i.e. less than $90, then it should be Green
  • If Actual is within +/- 10% of Budget  i.e. Between $90 and $110,  then Yellow
  • If Actual is 10 % Greater Than budget i.e. Greater than 110 then Red

 

Its a complete opposite scenario then Sales. 

 

No if my Actual cost is $120 with $100 budget then Guage should show Green Area from $0-90, yellow $91-110 , Red for above $110. And the pointer should be in Red area.  In the Image below the green area and red area should be switched and pointer should saty in same position but Red because Actual cost exceeded the Budget.

 

 

 

purana2002 Regular Visitor
Regular Visitor

Re: Budget vs Actual Cost Analysis with Dial Guage

This is exactly I want in POWER BI,

 

http://www.airtmagic.com/speedo-gauge

otravers Member
Member

Re: Budget vs Actual Cost Analysis with Dial Guage

purana2002 Regular Visitor
Regular Visitor

Re: Budget vs Actual Cost Analysis with Dial Guage

Thank you, I was able to achieve it with tachometer.

Helpful resources

Announcements
Can You Solve These Challenge

Challenge: Can You Solve These?

Find out how to participate in the first Power BI 'Can You Solve These?' challenge.

Community News & Announcements

Community News & Announcements

Get your latest community news and announcements.

Virtual Launch Event

Microsoft Business Applications October Virtual Launch Event

Join us for an in-depth look at the new innovations across Dynamics 365 and the Microsoft Power Platform.

Community Kudopalooza

Win Power BI Swag with Community Kudopalooza!

Each week, complete activities and be qualified in the drawing for cool Power BI Swag.

Users Online
Currently online: 53 members 1,140 guests
Please welcome our newest community members: