Adding indentation and hierarchy to a list of project tasks

I have project tasks in this format. 

image.png

 

P1 is the main task with two sub tasks Summary Task 1 and Summary Task 2. Summary Task 1 in turn has two sub tasks ST-Task 1 and ST-Task 2.  I only have two levels of hierarchy, as indicated by "Indentation Level" column - 0, 1 and 2. I am trying to achieve the following result(s) - group the tasks under each parent task and achieve the following result - and show this with some level of visual indentation (indicated in "Spaced Out Task Name" column) as follows:

 

image.png

 

I got the spacing worked out as a separate column with CONCATENATE but this is not showing up on the visual. Also not able to group the tasks as shown above. Thank you. Here is the pbix that I am using.

 

PS: I am using table visual. I tried the matrix visual and adjusted 'row headers' and stepped layout, but did not get the desired result. 

2 ACCEPTED SOLUTIONS

Accepted Solutions
Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

Hi @ek2112

 

Looks like the HTML is removing the spaces.

 

Please try this alternative

 

New Column = 
    REPT(
        REPT(UNICHAR(127),2),
        PATHLENGTH(
            PATH('Tasks'[Task ID],'Tasks'[ParentTaskID])
            )
        ) & 'Tasks'[Task Name]

To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

Adding this calculated column allows you to control the sort

 

Task ID Sort = SUBSTITUTE(PATH('Tasks'[Task ID],'Tasks'[ParentTaskID]),"|",".")

image.png


To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

10 REPLIES 10
Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

Hi @ek2112

 

Please try adding the following calculated column to your model

 

New Column = 
    REPT(
        REPT(" ",4),
        PATHLENGTH(
            PATH('Tasks'[Task ID],'Tasks'[ParentTaskID])
            )
        ) & 'Tasks'[Task Name]

image.png


To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

ek2112 Member
Member

Re: Adding indentation and hierarchy to a list of project tasks

Hi @Phil_Seamark

 

Thanks for looking into this. I have added the column, groups fine, but I am not able to get the indentation on the visual - table or matrix - not sure what I am doing wrong. Here is the updated pbix

 

image.png

Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

Hi @ek2112

 

Looks like the HTML is removing the spaces.

 

Please try this alternative

 

New Column = 
    REPT(
        REPT(UNICHAR(127),2),
        PATHLENGTH(
            PATH('Tasks'[Task ID],'Tasks'[ParentTaskID])
            )
        ) & 'Tasks'[Task Name]

To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

Highlighted
ek2112 Member
Member

Re: Adding indentation and hierarchy to a list of project tasks

@Phil_Seamark - got it! It works fine, but now the hierarchy got messed up. Is there any way that the grouping of child tasks are based on the parent task id regardless of their 'task id'? ST-Task 1 and ST-Task 2 should be under Summary Task 1 as their "ParentTaskID" is 1. Thank you. Link to pbix.

 

image.png

ek2112 Member
Member

Re: Adding indentation and hierarchy to a list of project tasks

@Phil_Seamark just wanted to clarify that I need to group the child tasks under parent tasks based on parent task ID and display them in the order of parent task ids.

Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

You probably need another column that contains something that can be sorted by.

 

eg. a list like

1

1.1

1.1.1

1.1.2

1.2

1.2.1 

2

2.1

2.1.1

2.1.2

... etc

etc....  

 

Would that be ok to include on your table visual to use to control sorting?


To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

Super User
Super User

Re: Adding indentation and hierarchy to a list of project tasks

Adding this calculated column allows you to control the sort

 

Task ID Sort = SUBSTITUTE(PATH('Tasks'[Task ID],'Tasks'[ParentTaskID]),"|",".")

image.png


To learn more about DAX visit : aka.ms/practicalDAX

Proud to be a Datanaut!

ek2112 Member
Member

Re: Adding indentation and hierarchy to a list of project tasks

@Phil_Seamark - brilliant. This worked like a charm. Thank you. I have to create a new WBS column to get this, but this helps a lot.

alejandram5 Frequent Visitor
Frequent Visitor

Re: Adding indentation and hierarchy to a list of project tasks

I think I found an easier way to do it using IF , so you dont have to add two extra columns, just an extra column that indicates if is a total - subtotal - detail

 

New Column =
IF('MS (3)'[Filter] = "Detail",
REPT(" ",9) & 'MS (3)'[Account], IF('MS (3)'[Filter] = "Subtotal",
REPT(" ",6) & 'MS (3)'[Account], 'MS (3)'[Account]))
 
my column account is the name of the account and my  column Filter tolds me if is detail, total or subtotal.
 
I hope it works for you