SUM data between two dates excluding weekends

hi. i want to sum across the next 5 working days 

5 days added to the date 4/8/20 is 9/8/20 so excludes the 10/8/20

I have a dim_date table with a working_day flag.

Does anyone have thoughts on a nifty way to either move  forward '5 rows" im dim_date and get the date in that row (i.e 10/8/20) OR

SUM across 5-rows ub the fact_data table rather than use DATESBEWTEEN()

thanks     

serge1_0-1596609770307.png

 

 

1 REPLY 1
amitchandak
Super User
Super User

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.

Top Solution Authors