Need help with Daily Resource Loading for Production Elements (DAX to calculate load per day)

Hello, 

From our ERP system I have data on:
[Resource Name] (Machine Centre)
[Project Name]
[Start Date]
[End Date]
# of [Hrs of Work] required

I am trying to make a stacked bar chart that shows each day, with a slicer to filter per [Resource Name], showing which projects are being processed on on the days shown. 

Right now I can make a stacked bar with all of the work showing up on the [End Date], but what I need to do is divide the [Hours of work] between the [start date] and the [end date], thus showing how much work is to be done on each project per day.

Thanks,  

1 ACCEPTED SOLUTION
amitchandak
Super User IV
Super User IV

@nick_SMTC , refer if the blog or my file on similar topic attached after signature can help


https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-o...

 

 



Did I answer your question? Mark my post as a solution! Appreciate your Kudos!!
Dashboard of My Blogs !! YouTube Channel !! Connect on Linkedin

Proud to be a Super User!

View solution in original post

3 REPLIES 3
amitchandak
Super User IV
Super User IV

@nick_SMTC , refer if the blog or my file on similar topic attached after signature can help


https://community.powerbi.com/t5/Community-Blog/How-to-divide-distribute-values-between-start-date-o...

 

 



Did I answer your question? Mark my post as a solution! Appreciate your Kudos!!
Dashboard of My Blogs !! YouTube Channel !! Connect on Linkedin

Proud to be a Super User!

View solution in original post

Thanks amitchandak, 

 

 I was able to get the solution to work with some fine tuning. Top graph is what I had before and bottom graph is what I was able to cut it into in terms of daily resource use.  Much appreciated!!

nick_SMTC_0-1619136856438.png

 

Thanks amitchandak, got the date table working but having trouble with the formulas to assign a volume of work per date. Will continue to work on. 

Helpful resources

Announcements
PBI User Groups

Welcome to the User Group Public Preview

Check out new user group experience and if you are a leader please create your group!

MBAS on Demand

Microsoft Business Applications Summit sessions

On-demand access to all the great content presented by the product teams and community members! #MSBizAppsSummit #CommunityRocks

MBAS Attendee Badge

Claim Your Badge & Digital Swag!

Check out how to claim yours today!

secondImage

Are You Ready?

Test your skills now with the Cloud Skills Challenge.

Top Solution Authors