Duration to time

Hi Community, 

I have a column with a duration in sec.

I need to transform this into time HH:MM:SS

First, I did 3 new columns:

-Hour = ROUNDDOWN(table[duration]/3600,0) 

-Minute = ROUNDDOWN((table[duration]-table[Hour]*3600)/60,0)

-Second = table[duration] - (table[Hour]*3600 + table[Minute]*60)

Now that I have the hours, minutes and seconds, I want to get all together in a time format:

-Time = time(table[Hour], table[Minute],table[Second])

 

But, I'm having 2 issues:

The first one is that the time is not shown only as HH:MM:SS but as 30/12/1899 HH:MM:SS
The second one is that in some cases the calculation is not working, for example there are durations with 94 minutes (that should be 1 hour and 34 minutes)

1.png

3 REPLIES 3
natabird3 Member
Member

Re: Duration to time

To be honest i do not think you will be able to make it work in Power Bi to dispaly this way. I have tried many options, and unfortunately currently is not supported as far as i am aware. 

davidtabacman Regular Visitor
Regular Visitor

Re: Duration to time

I think you are right.

I tried another 2 totally different ways, that logically should work, and get the same (mistaken) result.

 

thampton Member
Member

Re: Duration to time

@davidtabacman If you are wanting to use a measure and not a column , ive had success with the measure below. All you need is a measure that sums up the seconds. 

 

Duration = // Duration formatting
// * @konstatinos 1/25/2016
// * Given a number of seconds, returns a format of "hh:mm:ss"
//
// We start with a duration in number of seconds
VAR Duration = *Put your measure here*
// There are 3,600 seconds in an hour
VAR Hours =
INT ( Duration / 3600)
// There are 60 seconds in a minute
VAR Minutes =
INT ( MOD( Duration - ( Hours * 3600 ),3600 ) / 60)
// Remaining seconds are the remainder of the seconds divided by 60 after subtracting out the hours
VAR Seconds =
ROUNDUP(MOD ( MOD( Duration - ( Hours * 3600 ),3600 ), 60 ),0) // We round up here to get a whole number
// These intermediate variables ensure that we have leading zero's concatenated onto single digits
// Hours with leading zeros
VAR H =
IF ( LEN ( Hours ) = 1,
CONCATENATE ( "0", Hours ),
CONCATENATE ( "", Hours )
)
// Minutes with leading zeros
VAR M =
IF (
LEN ( Minutes ) = 1,
CONCATENATE ( "0", Minutes ),
CONCATENATE ( "", Minutes )
)
// Seconds with leading zeros
VAR S =
IF (
LEN ( Seconds ) = 1,
CONCATENATE ( "0", Seconds ),
CONCATENATE ( "", Seconds )
)
// Now return hours, minutes and seconds with leading zeros in the proper format "hh:mm:ss"
RETURN
CONCATENATE (
H,
CONCATENATE ( ":", CONCATENATE ( M, CONCATENATE ( ":", S ) ) )
)

Helpful resources

Announcements
Exclusive LIVE Community Event #3 – Ask Arun Anything

Exclusive LIVE Community Event #3 – Ask Arun Anything

Join us in the third Triple A event!

Meet the 2020 Season 1 Power BI Super Users!

Meet the 2020 Season 1 Power BI Super Users!

It’s the start of a new Super User season! Learn all about the new Super Users and brand-new tiered recognition system.

Super User Challenge: Can You Solve These?

Super User Challenge: Can You Solve These?

We're celebrating the start of the New Super User season with our first ever Super User 'Can You Solve These?' challenge.

January 2020 Community Highlights

January 2020 Community Highlights

Make sure you didn't miss any of the things that happened in the community in January!

Top Solution Authors
Top Kudoed Authors