Schedule a refresh/multiple attempts in each refresh

Hello,

I've scheduled a refresh in service every 30 minutes. Previously, if the refresh attempt failed, it would automatically retry. But, as of now, if it fails once, it won't attempt to refresh again. Do I need to change a configuration setting? I think Power BI will try 4 times in a row and if all 4 tries fail, it will disable the scheduling. 

The error is regarding hitting the memory limit of the premium capacity.

1:

hoosha_11_0-1713872170563.png

2:

hoosha_11_1-1713872178175.png

 

3 REPLIES 3
audreygerred
Super User
Super User

Do you have Premium Capacity? If so, what SKU do you have? What is the size of the model you are trying to refresh? Full refresh or incremental?




Did I answer your question? Mark my post as a solution!

Proud to be a Super User!





Yes, we have PPU (embedded) capacity with A2 size (5GB memory). I have implemented incremental refresh policy on 2 large tables (to refresh last 12 months). 

Vertipaq analyzer in DAX studio shows 1.05GB loaded into the memory in last refresh. 

Check out this YouTube from Guy in a Cube and Marco Russo that explains the model size how it is different in different places and some reasons why: What's the real size of your data model in Power BI? (youtube.com)




Did I answer your question? Mark my post as a solution!

Proud to be a Super User!





Helpful resources

Announcements
RTI Forums Carousel3

New forum boards available in Real-Time Intelligence.

Ask questions in Eventhouse and KQL, Eventstream, and Reflex.

MayPowerBICarousel1

Power BI Monthly Update - May 2024

Check out the May 2024 Power BI update to learn about new features.

Top Solution Authors