Using Earlier Value

Capture.PNG

I would like to do a calucation that divides the first column by the previous second column value. How would I do this?

 

For example for 201805 the calculation would be 2337/247945 and for 201804 it would be 2228/240730....etc.

1 ACCEPTED SOLUTION
Zubair_Muhammad
Community Champion
Community Champion

@Anonymous

 

Assuming first column in the Matrix is named "MonthYear"...try this MEASURE

 

Measure =
DIVIDE (
    SUM ( Table1[Col1] ),
    CALCULATE (
        SUM ( Table1[Col2] ),
        FILTER (
            ALL ( Table1[MonthYear] ),
            Table1[MonthYear]
                = MAX ( Table1[MonthYear] ) - 1
        )
    )
)

Regards
Zubair

Please try my custom visuals

View solution in original post

1 REPLY 1
Zubair_Muhammad
Community Champion
Community Champion

@Anonymous

 

Assuming first column in the Matrix is named "MonthYear"...try this MEASURE

 

Measure =
DIVIDE (
    SUM ( Table1[Col1] ),
    CALCULATE (
        SUM ( Table1[Col2] ),
        FILTER (
            ALL ( Table1[MonthYear] ),
            Table1[MonthYear]
                = MAX ( Table1[MonthYear] ) - 1
        )
    )
)

Regards
Zubair

Please try my custom visuals

Helpful resources

Announcements
Microsoft Fabric Learn Together

Microsoft Fabric Learn Together

Covering the world! 9:00-10:30 AM Sydney, 4:00-5:30 PM CET (Paris/Berlin), 7:00-8:30 PM Mexico City

PBI_APRIL_CAROUSEL1

Power BI Monthly Update - April 2024

Check out the April 2024 Power BI update to learn about new features.

April Fabric Community Update

Fabric Community Update - April 2024

Find out what's new and trending in the Fabric Community.